"KINGSTON – Town officials want to move forward with plans to remove the Independence wind turbine, but the turbine operator isn’t cooperating.
The town is asking a Superior Court judge to issue a ruling terminating Kingston’s lease and power purchase agreement with Kingston Wind Independence LLC due to the company’s failure to pay rent and taxes to the town in an amount exceeding $1.1 million.
Officials are also seeking an order from the court to allow the town or its representatives to enter onto the property to decommission and remove the turbine and related equipment."
Mon, Mar 21