NEWS: PJM cut Oklo’s 750-MW project from its streamlined interconnection process—and the next-gen nuclear developer is fuming.

  • The project is “of critical national importance,” according to the complaint Oklo filed with FERC on Friday. It includes 150 MW of advanced nuclear, 300 MW of fuel cells, and 300 MW of gas…but the partially redacted doc doesn’t reveal much else.

  • The conflict: Oklo claimed it provided PJM all the necessary info in April to enroll in its new “first-ready, first-served” queue study process. But the grid operator withdrew the project due to several “deficiencies” (including Oklo’s alleged failure to show that it could ride through an unexpected drop in grid voltage).

  • The consequences: Oklo said PJM’s decision will set back the project by over a year and prompt “adverse financial impact.” Now, the company wants FERC to order PJM to return the project to its queue spot. 👇