Energy Secretary Chris Wright is moving to fast-track grid connections for AI data centers and other large electricity users. (Latitude Media)
Wright’s plan outlines 13 guiding principles, including limiting interconnection studies to 60 days for flexible loads, requiring customers to pay full network upgrade costs, and studying hybrid facilities alongside generation.
The proposal would mark the first time FERC claims authority over large-load interconnections, arguing such facilities fall under its jurisdiction when tied to the interstate grid.
Yes, but: Legal experts question whether FERC can extend its reach so broadly—setting up a likely jurisdictional battle.