Temp check: As we reported, every FERC-regulated grid operator has asked for a three-month homework extension. But the mid-November deadline is looming—after all, pumpkin spice lattes are already hitting coffee shops. 🍂
SPP already meets one of FERC’s directives: It recently rolled out a speedy, non-firm interconnection service for large loads (known as CHILLS). But it’s also considering assigning full transmission upgrade costs—above a yet-to-be-determined limit—to large loads requesting service. SPP would require collateral in case these projects don’t materialize.
Get flexy: MISO, PJM, and CAISO are also working on flexible transmission service options, per FERC’s orders. 🤸
Thu, Aug 27
NEWS: Where are US grid operators at with FERC’s large-load orders? Here’s some highlights: