NEWS: PJM proposes an expedited interconnection track for generators to supply large load additions

PJM is proposing a new Expedited Interconnection Track (EIT) to fast-track large generators serving massive new loads—bypassing its traditional queue process. (Renewable Energy World)

  • Projects must exceed 500 MW, be state-sponsored, and reach commercial operation within three years—a high bar that likely favors battery storage over gas, wind, or nuclear.

  • Developers would shoulder all network upgrade costs and post a $10K/MW readiness deposit, capped at 10 projects per year.

  • PJM says the plan addresses capacity shortfalls tied to data center growth, but critics warn the requirements may be too ambitious to attract real projects.