In the Empire State, a new 100-mile, $1.5B transmission project is now complete. The new substations and rebuilt lines will broaden the reach of 1 GW of renewable energy. They’ll also offer over $400M in annual ratepayer savings, officials said. It’s part of the biggest investment in NY’s grid in five decades.
Down in AZ, Enlight has raised $2.6B for a 1.2-GW/4-GWh solar and storage project. It’s set to hit the grid beginning in 2027, and Enlight has inked deals with Salt River Project and Arizona Public Service.
Sun, Jun 28