What happened: On Monday, most FERC-regulated RTOs and ISOs hit the deadline for the agency’s show-cause orders. Meaning? They had to propose ways to make data center interconnections more efficient—while protecting ratepayers from cost-shifting.
According to FERC, that entails: 1) Creating streamlined study processes 2) offering service options designed for flexible large loads and 3) accommodating behind-the-meter generation, among other measures. Some highlights from the filings:
PJM unveiled a “Fast Energization” process to simultaneously study loads and generation. This could slash interconnection timelines from two years to one, the org said.
CAISO noted that its proposed reforms are tailored to its “distinctive market design,” and said its transmission owners will pursue cost-recovery provisions in their own tariffs.
ISO-New England is ordering new large loads to BYO capacity (given the region’s particularly tight supplies).
MISO has already sent FERC multiple large-load proposals, but recently floated cost-recovery agreements to shield ratepayers.