NEWS: Grid operators have answered FERC’s call for large-load interconnection rules. We’ve got the rundown.

  • What happened: On Monday, most FERC-regulated RTOs and ISOs hit the deadline for the agency’s show-cause orders. Meaning? They had to propose ways to make data center interconnections more efficient—while protecting ratepayers from cost-shifting.

  • According to FERC, that entails: 1) Creating streamlined study processes 2) offering service options designed for flexible large loads and 3) accommodating behind-the-meter generation, among other measures. Some highlights from the filings:

  • PJM unveiled a “Fast Energization” process to simultaneously study loads and generation. This could slash interconnection timelines from two years to one, the org said.

  • CAISO noted that its proposed reforms are tailored to its “distinctive market design,” and said its transmission owners will pursue cost-recovery provisions in their own tariffs.

  • ISO-New England is ordering new large loads to BYO capacity (given the region’s particularly tight supplies).

  • MISO has already sent FERC multiple large-load proposals, but recently floated cost-recovery agreements to shield ratepayers.