NEWS: Data centers in Nvidia’s hometown stand empty awaiting power

Two massive data centers in Santa Clara, California—just blocks from Nvidia’s HQ—are sitting dark as the city’s utility struggles to deliver power. (Fortune)

  • Digital Realty and Stack Infrastructure each built 48-MW facilities that can’t go live until Silicon Valley Power finishes a $450M system upgrade, expected in 2028.

  • Developers say power delays of 3 to 7 years are now common in high-demand regions like Silicon Valley and Northern Virginia.