NEWS: CAISO’s new plan for managing large loads.

  • Deadline approaching: Grid operators have until mid-November to tell FERC how they’re going to seamlessly bring new large loads onto the grid.

  • The latest: CAISO’s draft proposal centers on “proactive transmission planning, generator interconnection, and operational reliability.” It suggests defining large loads as 50 MW or greater. 

  • Building the plane while flying it? To speed up connection, CAISO intends to create a framework to allow large users to plug-in quickly and start receiving some amount of power (not specified), “while waiting for network upgrade completion.”