Six Per Cent of the Claims. Eighteen Million Dollars Each.

Read here: https://medium.com/@donfackfortune/six-per-cent-of-the-claims-eighteen-million-dollars-each-14efbbff1ee0?sharedUserId=donfackfortune


This piece examines a question offshore transmission owners face directly and that the published statistics answer poorly: what actually drives the severity of an export-cable loss?

The sector's most-quoted figure β€” 80% of European offshore wind insurance claims cable-related, 62% of those from construction damage β€” originates in the Carbon Trust's CTC835 cable burial methodology (February 2015), which attributes it to information from insurance brokers and underwriters rather than to a measured population. AXIS Global Energy's more recent portfolio review (published 4 March 2026, covering January 2021 to September 2025) reports export cables at 6% of claim count with the sector's highest average claim, $18.8 million.

Working backwards from the measured figure, the article argues that severity is governed by outage duration rather than by cable cost: cable supply and installation is 8–12% of CAPEX, average UK export-cable downtime is 62 days, and at Beatrice this year a 38-day repair sat inside an outage of roughly three months. The Africa layer treats the cost-of-capital consequence for interconnector projects, where no regional repair capacity exists.

Sources

  • AXIS Capital, AXIS Offshore Wind Report Highlights Technical Risks and Evolving Challenges, 4 March 2026 (portfolio January 2021 – September 2025).

  • The Carbon Trust, Cable Burial Risk Assessment Methodology: Guidance for the Preparation of Cable Burial Depth of Lowering Specification, CTC835, February 2015.

  • Strang-Moran, C., Subsea cable management: failure trending for offshore wind, Offshore Renewable Energy Catapult; Wind Energy Science preprint wes-2020-56, 30 March 2020 (CC BY 4.0).

  • DNV, 80% of insurance claims in offshore wind are related to subsea cable failures β€” how can the industry manage these risks?

  • DESNZ, Regional renewable electricity in 2024, 30 September 2025 (Table 2, load factors).

  • IEA, How a high cost of capital is holding back energy development in Kenya and Senegal, 6 February 2025; IEA Cost of Capital Observatory.

  • UK Written Ministerial Statement HCWS745, Michael Shanks MP, DESNZ, 26 June 2025 (Xlinks Morocco–UK Power Project).