Vistra has asked FERC for a two-year interconnection extension for Illinois solar and battery projects due to supply chain delays in MISO. (Utility Dive)
The two projects, which total 833 MW of solar and battery storage, have been in development since at least 2022.
Now, as Vistra sees multi-year wait times to acquire key equipment, connecting those projects to the grid could take until mid-2030.